Engineering for a Plastic Waste Pyrolysis Plant

Project Sheet

Sector

Industrial plants

Country

Spain

Scope

3D, Basic engineering, CAPEX

Year

2025

Customer

URBASER S.A.

EIA21 developed the basic engineering and CAPEX estimation required to scale up a chemical recycling pilot plant based on plastic waste pyrolysis, enabling the production of recycled pyrolysis oil for circular economy applications.

Engineering for a Plastic Waste Pyrolysis Plant

The Challenge

To scale an operational chemical recycling pilot plant in Zaragoza into an industrial-scale facility while delivering a reliable CAPEX estimate with an accuracy of ±25%.
The main challenge was to technically define a larger-scale plant with a processing capacity of 15,000 tonnes of raw plastic waste per year and 10,500 tonnes of refined product per year, integrating multiple disciplines, technologies and industrial processes into a viable and cost-effective solution.

The Solution

EIA21 developed a comprehensive basic engineering package focused on the technical definition of the plant and the economic assessment of its industrial-scale deployment.
The scope of work included:

  • Industrial-scale conceptual and technical plant definition
  • Development of 3D models for layout and configuration analysis
  • Identification and specification of major process equipment
  • Request for quotations from specialist suppliers and contractors
  • Collection of real market pricing data for key disciplines, including mechanical, electrical, instrumentation & control, civil works and structural engineering

This approach created a robust and realistic basis for the CAPEX estimate, significantly reducing investment uncertainty.

Results

The project provided the client with a reliable investment estimate based on real market data for the industrial deployment of its pyrolysis technology.
Key project achievements included:

  • CAPEX estimation with ±25% accuracy
  • Clear technical definition of the industrial facility
  • Identification of major equipment and installation scope
  • Collection of real market pricing for equipment and construction activities
  • Reduced investment decision-making risks

The project established the foundation for the industrial development of a solution focused on plastic waste valorization and the production of alternative raw materials, supporting the transition towards a circular economy.